Park Farm, Madingley - Update

ACP has just completed installation of the precast concrete walling to the new calf/lambing shed at the Cambridge University Farm as part of a major redevelopment of their facilities. The existing buildings had reached the end of their useful lives and no longer provided facilities acceptable to the regulatory bodies, including the Royal College of Veterinary Surgeons. Replacement facilities were required if farm animal veterinary teaching was to continue. The new development also allows for redevelopment of the existing buildings.

 

 Working as a subcontractor to R G Carters, ACP won this contract following on from a project earlier in the year to supply and install walling to the new silage clamp. ACP also supplied precast wall panels via Shufflebottom Ltd to the grain store and youngstock buildings on the farm. The farm totals 925 hectares and the redevelopment will cost approx. £2.6m

 

 
 